HR

Transmission line from Ernestinovo to the border with Hungary energized

26.02.2010.
Today at 10:16 the newly built transmission line 2 x 400 kV Ernestinovo-Pecs was put into trial operation, from the Ernestinovo substation to the state border with Hungary.

The energizing is part of the necessary tests and measurements along the route of the transmission line which runs for 44.1 km through the cadastral municipalities of Orlovnjak, Ivanovac, Čepin, Josipovac, Petrijevci, Darda, Jagodnjak, Bolman, Petlovac, Šumarina and Luč. The energizing was led by Branko Štefić, head of Area Network Control Section of Osijek Transmission Area of HEP OPS in the presence of transmission area directors from all over Croatia headed by assistant director of HEP OPS, Igor Ivanković.